The Thermal Repair Process
  1. The area for the repair is cleaned.  All debris is removed
  2. A perimeter at least 6” from the defect is heated by the EZ Pavement Repair Infrared Heater.  This take less than 10 minutes.
  3. The asphalt is now close to its original state, meaning softened by the heating process, and is scarified.
  4. Workers add new asphalt as needed and spray asphalt oil to rejuvenate the pavement.  100% of the existing asphalt is recycled.
  5. The surface is now leveled.  This is called luting.
  6. Now that the surface is level it is compacted with a roller or plate compactor.
Because this is a thermal bond, the repair is fused to the existing pavement.  This restores the pavement back to a continuous surface level with the existing asphalt eliminating seams.  This also reduces damage caused by normal traffic, snow plows and other hazards inherent to traditional repairs.



 

 